Batch Registration: 10 May & 25 May 2026
+918988885050
It has come to our attention that certain coaching centers are misusing names similar to ours, such as Vajirao or Bajirao, in an attempt to mislead and attract students/parents. Please be informed that we have no association with these fake institutes and legal proceedings have already been initiated against them before the Hon'ble Delhi High Court. We urge students and parents to stay vigilant and let us know in case they are approached by such fake institutes.
Home
Our Courses
Classroom Courses
Online Live Courses
Weekend Courses
Recorded Lectures
Optional Courses
Test Series
Correspondence Courses
Exclusive UPSC Crash Course
GS Advance Course
Exclusive Current Affairs Program
Essay Course
Mentorship Program
Fees Structure
New Batches
Online Registration
Study Materials
Current Affairs
News Analysis English
News Analysis Hindi
Yojana Magazine Analysis
Mains Answer Writing
UPSC IAS Syllabus
Previous Year Papers
Monthly Magazine
Blogs
State PCS Exams
Selections
IAS Results
PCS Results
Topper Videos
Enquiry
MEIL & RATLE HEP ISSUE
from Vajirao & Reddy Institute
Current Affairs
MEIL & RATLE HEP ISSUE
By : Author Desk
Updated : 2025-12-13 11:50:44
MEIL & RATLE HEP ISSUE
Why in News?
Megha Engineering and Infrastructures Ltd. (MEIL)
has stated that it may
withdraw from the 850 MW Ratle Hydroelectric Project
in
Kishtwar district of Jammu and Kashmir
if
threats, political interference, and pressure on workers
are not stopped.
ABOUT RATLE HEP
Capacity:
850 MW
Type:
Run-of-the-river hydroelectric project
River:
Chenab
Location:
Kishtwar district, Jammu and Kashmir
Approved:
2021
Estimated cost:
5,281.94 crore
Scheduled commissioning:
May 2026
IMPLEMENTING AGENCY
Implemented by
Ratle Hydroelectric Power Corporation Limited (RHPCL)
RHPCL is a
joint venture
between:
NHPC
– 51 percent equity
Jammu and Kashmir State Power Development Corporation (JKSPDC)
– 49 percent equity
Construction contractor:
Megha Engineering and Infrastructure Limited (MEIL)
TECHNICAL FEATURES
Concrete gravity dam
Height:
133 metres
Length:
194.8 metres
Includes a
diversion dam
Underground powerhouse
located on the right bank of the Chenab
Powerhouse dimensions:
168 m x 24.5 m x 49 m
Turbine configuration:
Four
205 MW Francis turbine units
One
30 MW auxiliary turbine
Expected annual generation:
3,137 GWh of electricity
ISSUE RAISED BY MEIL
Workers facing
threats and intimidation
Political pressure
to hire additional local workers despite no vacancies
Interference affecting
project execution
Concern that safety and construction quality may be compromised
Triggering Incident
On
4 December 2025
, MEIL’s
HR head was allegedly attacked
The incident created fear among workers at the project site
EMPLOYMENT SITUATION
Total workforce:
1,434
From Kishtwar:
900
From nearby districts:
244
From outside the region:
215
, due to specialised technical requirements
MEIL stated it cannot meet
forced hiring demands
when no vacancies exist.
INTERNATIONAL DIMENSION
Pakistan has repeatedly objected
to the Ratle project
Allegations claim violation of the
Indus Waters Treaty, 1960
India maintains that Ratle is a
run-of-the-river project
, permissible under the Treaty
WHY THIS ISSUE MATTERS?
Ratle is a
strategically important power project
for Jammu and Kashmir
Delays or withdrawal could affect
regional energy security
Raises concerns about:
Law and order at infrastructure sites
Investment climate in sensitive regions
Balancing local employment and technical needs.